The National Environmental Policy Act and Outer Continental Shelf Oil and Gas Activities

From The Encyclopedia of Earth
Jump to: navigation, search
The Deepwater Horizon disaster. Credit: Washington Dept. of Ecology

The National Environmental Policy Act and Outer Continental Shelf oil and gas activities

February 9, 2011, 12:00 am
June 1, 2011, 6:33 am
Source: National Commission on the BP Deepwater Horizon Oil Spill and Offshore

Editor's Note: This article is excerpted directly from National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling (National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling), "The National Environmental Policy Act and Outer Continental Shelf Oil and Gas Activities," Staff Working Paper No. 12. It has been edited only to conform to the Encyclopedia's style guidelines.


This staff working paper focuses on the National Environmental Policy Act of 1969 (NEPA) and its application to offshore oil and gas activities. The paper is divided into three sections. The first section is a general discussion of NEPA as it applies to Federal agencies. The second section addresses the Department of the Interior’s (DOI) NEPA regulations and portions of its [Manual] that relate to the implementation of those rules for oil and gas activities. The third section focuses on NEPA questions specific to the Deepwater Horizon oil spill.

Operation of NEPA

Procedural Nature of NEPA

On May 24, 2010, the Terra satellite captured sunlight illuminating the growing oil slick off the Mississippi Delta. Credit: NASA

NEPA establishes a process by which federal agencies are obligated to review the environmental effects of their proposed agency actions during the decision-making process. While NEPA’s underlying purpose is to reduce environmental degradation, the nature of the obligation that the statute imposes on agencies to review the impacts of their decisions is essentially procedural. The statute is designed to require federal agencies to prepare formal “statements” in which proposed agency actions are analyzed in a way that promotes informed decision-making rather than a substantive result. Thus, NEPA’s goal is not to prevent federal approval of actions that might have environmental consequences, but instead to ensure that agency actions are undertaken knowingly and made in consideration of potential environmental consequences.

The Supreme Court articulated this statutory purpose in the early decades of NEPA’s implementation, in the context of its review of NEPA-compelled agency statements. The Court made clear that NEPA is designed to “insure a fully informed and well-considered decision.”1 The statute requires agencies to take a “hard look” at environmental effects of a major federal action,2 but it does not require agencies “to elevate environmental concerns over other appropriate considerations.”3 NEPA does not bar environmentally-destructive actions,4 to promote environmental protection by ensuring rigorous and timely consideration of environmental consequences:

NEPA does not work by mandating that agencies achieve particular substantive environmental results. Rather, NEPA promotes its sweeping commitment to “prevent or eliminate damage to the environment and biosphere” by focusing Government and public attention on the environmental effects of proposed agency action.5 By so focusing agency attention, NEPA ensures that the agency will not act on incomplete information, only to regret its decision after it is too late to correct.6

The Court also clarified that NEPA is about process and informed decision-making:

NEPA does not mandate particular results, but simply prescribes the necessary process. . . . If the adverse environmental effects of the proposed action are adequately identified and evaluated, the agency is not constrained by NEPA from deciding that other values may outweigh environmental costs. . . . Other statutes may impose substantive environmental obligations on Federal agencies, but NEPA merely prohibits uninformed—rather than unwise—agency action.7

NEPA’s Action-Forcing Requirement—a Detailed Statement

Section 102(2) is the operative provision with respect to NEPA documents.8 Subsection (A) directs agencies to “utilize a systematic, interdisciplinary approach which will insure the integrated use of the natural and social sciences and the environmental design arts in planning and in decisionmaking which may have an impact on man’s environment.” The directive for preparation of NEPA documents in association with agency action appears in subsection (C), which requires a “detailed statement by the responsible official.” Specifically, subsection (C) requires an agency to consider potential environmental impacts of a proposed action if that action is a “major Federal action[] significantly affecting the quality of the human environment.”9 The agency must adequately discuss not only the environmental impact of the proposed action, but also its unavoidable adverse impacts, alternatives to it, the relationship between short-term uses of the environment and long-term productivity, and any irreversible commitments of resources resulting from the proposed action.10 In addition, subsection (E) requires the agency to “study, develop, and describe appropriate alternatives to recommended courses of action in any proposal which involve[] unresolved conflicts concerning alternative uses of available resources.”11

Non-federal action is not subject to NEPA, but can fall under the statute’s purview if an agency approves some aspect of the action. Actions that do not have the potential for significant environmental effects are, however, not subject to NEPA’s requirement that a federal agency prepare a detailed statement that considers the environmental impacts of the agency’s proposed action.12

CEQ Regulations

Title II of NEPA established the Council on Environmental Quality (CEQ) within the Executive Office of the President. By Executive Order 11991(May 24, 1977), President Jimmy Carter directed CEQ to “[i]ssue regulations to Federal agencies for the implementation of the procedural provisions” of NEPA. The resulting regulations, first promulgated on November 28, 1978, and later amended, set forth the manner by which agencies implement NEPA section 102(2).13 The regulations, which are binding “except where compliance would be inconsistent with other statutory requirements,”14 require agencies to establish their own procedures to implement NEPA in consultation with CEQ.15

NEPA Documents

BP’s crisis command center in Houston, Texas, was called the HIVE because it offered a highly immersive visualization environment. From these consoles, command center staff controlled 40 to 60 ships and 12 to 16 remotely operated vehicles during containment and oil-recovery operations. Credit: BP PLC

Under NEPA section 102(2)(C), any agency action that has a potential to significantly affect the quality of the human environment must be accompanied by NEPA review. CEQ regulations employ two documents that outline environmental impacts: an environmental impact statement (EIS) and an environmental assessment (Environmental Impact Assessment) (EA).16 The EIS is the “detailed statement” identified in NEPA to address a major Federal action that has significant impacts on the human environment.17 By contrast, an EA is a “concise public document” that serves to (1) briefly provide sufficient evidence and analysis for determining whether to prepare an EIS; (2) aid an agency’s compliance with NEPA when no EIS is necessary; and (3) facilitate preparation of an EIS when one is necessary.18

The point of an EA is to document whether an EIS is required for a proposed action. If an agency knows that an action will generate significant environmental effects, an EIS is required and there is no basis for preparing an EA. But if the agency is unsure, or if the proposed action is of the sort that does not always require an EIS,19 the agency may prepare an EA. If, as a result of an EA, the agency determines that no significant impact will likely result from the proposed action, the agency issues a “finding of no significant impact” (FONSI).20 A FONSI may include the discussion underlying its conclusion, or may attach an EA.21 If an agency issues a FONSI, NEPA compliance is complete because, as a statutory matter, the proposed action will not significantly affect the human environment, and thus a detailed EIS is unnecessary.22 By contrast, if the analysis in an EA projects a significant impact, an agency cannot issue a FONSI. If an agency wishes to move forward with a proposed action, it must choose an alternative that mitigates impacts such that a FONSI is warranted,23 or it must prepare a full EIS.24

The EIS, EA, and FONSI, are three of four “environmental documents” which effectuate NEPA’s mandatory review.25 The fourth is a Notice of Intent, which is a public notice that an EIS will be prepared.26 No other NEPA documents exist in the CEQ rules to accomplish the NEPA review required in section 102(2).

When and How to Prepare an EIS or an EA

An agency can always choose to prepare an EIS, and must do so if the action is one “normally requiring” an EIS.27 The scope and format of the EIS is controlled by regulations that require a summary, a section describing the purpose and need for the proposed action, alternatives to it, the affected environment, environmental consequences from the action, and a list of preparers.28 The EIS generally must be circulated to other agencies and is subject to consultation with relevant members of the public and governmental entities.29 An EA is less detailed, more concise, and prepared for actions that might have no significant impacts, or ones that can be reduced to a level of “not significant” with mitigation. Considerably less of an investment than an EIS, EAs include “brief discussions of the need for the proposal, of alternatives as required by section 102(2)(E), of the environmental impacts of the proposed action and alternatives, and a listing of agencies and persons consulted.” 30

The distinctions between an EA and an EIS give rise to common misconceptions about them. One misconception is that when an agency prepares a full EIS, its work is devoted to preventing all significant impacts. However, by its nature, although an EIS considers significant impacts, it is not a prescription for avoiding them.31 An agency prepares an EIS because significant impacts are anticipated.32 Therefore, the fact that an EIS identifies adverse impacts is not tantamount to a failure of NEPA compliance. Indeed, in Robertson v. Methow Valley Citizens Council, the Supreme Court rejected the idea that an EIS can only be sustained if it provides for detailed mitigation of all potential impacts:

There is a fundamental distinction, however, between a requirement that mitigation be discussed in sufficient detail to ensure that environmental consequences have been fairly evaluated, on the one hand, and a substantive requirement that a complete mitigation plan be actually formulated and adopted, on the other. . . . [I]t would be inconsistent with NEPA’s reliance on procedural mechanisms—as opposed to substantive, result-based standards—to demand the presence of a fully developed plan that will mitigate environmental harm before an agency can act.33

Another misconception is that if an EA is prepared, a FONSI necessarily must result because the EA/FONSI together identify any significant impacts from the proposed action. However, an EA can never constitute final NEPA compliance if it is the vehicle for identifying significant impacts that cannot be mitigated. While it is enough that significant impacts have been fully vetted in an EIS, they must be reduced to a level of “not significant” in an EA for a FONSI to result. An EA is sufficient to conclude NEPA compliance and to lead to a FONSI only if it justifies a conclusion that no significant impacts will occur as incremental effects of the proposed action. If this is not the result then further NEPA documentation is required.

The sufficiency of NEPA documentation is determined ultimately by the federal courts in challenges to agency action under the Administrative Procedure Act.34 A party challenging a NEPA document must demonstrate with objective proof that the agency failed to adequately consider a substantial environmental question of material significance to the proposed action, or otherwise failed to abide by section 102(2) of NEPA. Proof of arbitrary or inconsistent conclusions, or a failure to consider relevant information, demonstrates a lack of compliance with NEPA because it proves an “arbitrary and capricious” action under the Administrative Procedure Act.35

An EIS is judged by whether it constitutes a “detailed statement” that takes a “hard look” at all of the potential significant environmental consequences of the proposed action and reasonable alternatives thereto, considering all relevant matters of environmental concern.36 The question is whether the EIS contains a “reasonably thorough discussion of the significant aspects of the probable environmental consequences” of the proposed action and alternatives.37 Significant impacts do not defeat an EIS under the Administrative Procedure Act.

By contrast, if an EA projects significant effects, a FONSI cannot be sustained and a challenge under the Administrative Procedure Act38 will prevail. An EA for which a FONSI has been issued will be affirmed when the record demonstrates that the agency has considered relevant matters of environmental concern, taken a “hard look” at potential environmental impacts, and made a convincing case that no significant impact will result or that any impact will be reduced to insignificance by the adoption of appropriate mitigation measures.39

Categorical Exclusions—Agency Actions Exempt from the Action-Forcing Requirements of NEPA

Following the failure of the top kill, BP engineers turned away from attempting to shut the well in, for fear that instability in the well could lead to an "underground blowout," with oil and gas flowing into the ocean from many points on the sea floor. This would make containment nearly impossible, at least until the completion of a relief well. Thus, in the aftermath of the top kill, BP and the government focused on trying to collect the oil, with the relief wells still providing the most likely avenue for killing the well altogether. Credit: Oil Spill Commission

Preparation of an EA or EIS that analyzes the effects of a proposed action and its reasonable alternatives is a procedural line an agency must cross before it can move forward with an action. CEQ has only included the EIS, EA, resulting FONSI (EA), and Notice of Intent (of an EIS) on its list of NEPA documents.40 CEQ understood, however, that NEPA does not, and should not, compel unnecessary paperwork.41 Therefore, CEQ identified “categorical exclusions” (CE)—sets of agency actions that do not generate environmental effects and thus are exempt from the case by case application of section 102(2). CEQ allows each agency to establish exceptions from the NEPA process for entire categories of actions, “which do not individually or cumulatively have a significant effect on the human environment and which are therefore exempt.”42 CEQ defines a CE as that “category of actions which do not . . . have a significant effect on the human environment and which have been found to have no such effect in procedures adopted by a Federal agency in implementation of the regulations43 and for which, therefore, neither an [EA] nor an [EIS] is required. . . . Any procedures under this section shall provide for extraordinary circumstances in which a normally excluded action may have a significant environmental effect.”44 A CE is thus not a level of NEPA review, but rather a defined category of agency action that does not require NEPA review apart from the development of the CE itself..

CEs represent the common sense notion that agencies routinely “act” in ways that do not create environmental effects requiring a “hard look.” For example, employee performance evaluations or organizational changes do not generate impacts on the physical world and thus are not subject to NEPA. In Sabine River Authority v. Department of the Interior,45 the Fifth Circuit held that “the acquisition of a negative easement which by its terms prohibits any change in the status quo does not amount to ‘major Federal action[] significantly affecting the quality of the human environment.’” Although, in this case, the court did not specifically define an agency-asserted CE, it did define a subset of actions exempt from NEPA as actions that do not change the physical world. The fact that an agency must examine a proposed action to determine whether it may properly be within a defined CE is an activity occasioned by NEPA, but the examination itself is not NEPA review in a NEPA document as defined by CEQ.

Agencies must establish a list of their own CEs, which are defined to be “categories of actions which do not individually or cumulatively have a significant impact on the human environment and are therefore exempt” from NEPA.46 Environmental documentation in the form of an EIS or EA is required unless an agency has established a procedure that includes identification of “typical classes of action . . . [w]hich normally do not require either an [EIS] or an [EA].”47

Effects/Impacts

In addressing the environmental consequences of a proposed action in an EIS, an agency must discuss both its direct and indirect effects as well as alternatives to the proposed action in order to offer meaningful comparisons to other actions that may also be implemented.48 Among the effects to be addressed are cumulative impacts49 and ways to mitigate effects.50 Similarly, EAs must include brief statements of “environmental impacts” of a proposed action.51

“Effects and impacts as used in these regulations are synonymous” and include “direct,” “indirect,” and “cumulative” effects.52 Direct effects are “caused by the action and occur at the same time and place.”53 Indirect effects are “caused by the action and are later in time or further removed in distance, but are still reasonably foreseeable. Indirect effects may include growth inducing effects and other effects related to induced changes in the pattern of land use, population density or growth rate, and related effects on air and water and other natural systems, including ecosystems.”54 A “reasonably close causal relationship” between the Federal action and the effects at issue is critical; where the chain of causation is unduly remote, an effect will not be deemed to be an indirect effect of a proposed action.55 A cumulative impact is the impact on the environment that results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions, regardless of what agency or person undertakes such other actions.56 Cumulative impacts can result from individually minor but collectively significant actions taking place over time.57

When certain impacts are to be analyzed depends on whether they may be reasonably foreseeable.

Worst Case Analysis

There is general confusion about whether agencies are required to consider a “worst case scenario” in their NEPA documents. At one time, regulations did require []to include worst case scenario analyses in certain circumstances. But CEQ eliminated this requirement in 1986 by revising its NEPA regulations. Worst case scenarios are not currently required in the NEPA regulations.

The worst case analysis requirement first arose in the 1978 CEQ regulations. CEQ was attempting to resolve how an agency should handle situations in which the impacts of an action were uncertain or unknown. It instructed federal agencies to obtain additional data when addressing “scientific uncertainty” or “gaps in relevant information” regarding significant adverse environmental effects that were “essential to a reasoned choice among alternatives” or “important to the decision.”58 The problem was that some such data was usually not available at all, or if available, unreasonably costly to obtain. Accordingly, if additional and necessary scientific information could not be acquired because the “overall costs of obtaining it were exorbitant,” or “the means for obtaining it were beyond the state of the art,” the agency was required to “include a worst case analysis and an indication of the probability or improbability of its occurrence.”59

CEQ amended the regulation in 1986. The change was controversial and generated considerable public comment. CEQ responded by explaining that it believed the 1978 regulation was “flawed” and that it needed to provide “better and more logical” requirements for agencies to deal with situations involving incomplete information.60 CEQ disagreed with the view expressed by certain commenters that removing the worst case scenario requirement would weaken NEPA compliance, instead stating that a “less sensational” and “more careful and professional approach” was a “better” way of dealing with incomplete and unavailable information in an EIS.61

In Robertson v. Methow Valley Citizens Council, the Supreme Court reversed a circuit court that had insisted the 1978 regulation’s demand for a worst case analysis be followed even after amendment of that regulation. The Supreme Court gave “substantial deference” to the 1986 regulatory amendment, citing the fact that the 1978 regulation had been subject to considerable criticism. Citing the 1985 proposed rule that became the 1986 amendments, the Court stated:

CEQ explained that by requiring that an EIS focus on reasonably foreseeable impacts, the new regulation “will generate information and discussion on those consequences of greatest concern to the public and of greatest relevance to the agency’s decision,” 50 Fed. Reg. 32237 (1985), rather than distorting the decision-making process by overemphasizing highly speculative harms, 51 Fed. Reg. 15624-15625 (1986); 50 Fed. Reg. 32236 (1985). In light of this well-considered basis for the change, the new regulation is entitled to substantial deference. Accordingly, the Court of Appeals erred in concluding that the EIS is inadequate because it failed to include a “worst case analysis.”62

The regulation in place today states that if “information relevant to reasonably foreseeable significant adverse impacts cannot be obtained” because it is too costly to get or unavailable, the agency must include a four-part statement regarding the information, including “the agency’s evaluation of such impacts based on theoretical approaches or research methods generally accepted in the scientific community.”63 “Reasonably foreseeable” environmental effects include “impacts which have catastrophic consequences, even if their probability of occurrence is low, provided that the analysis of the impacts is supported by credible scientific evidence, is not based on pure conjecture, and is within the rule of reason.”64

Consultation

Industry’s responsibilities do not end with efforts to prevent blowouts like that at the Macondo well. They extend to efforts to contain any such incidents as quickly as possible and to mitigate the harm caused by spills through effective response efforts. Credit: Oil Spill Commission

CEQ regulations establish extensive requirements for including other agencies and the public in the EIS process. CEQ’s stated policy is to encourage and facilitate “public involvement in decisions which affect the quality of the human environment.”65 The rules “emphasize agency cooperation early in the NEPA process.”66 In addition, they require “diligent efforts to involve the public in preparing and implementing their NEPA procedures.”67

The requirements for public and agency review of a pending EIS are demanding. The lead agency responsible for the proposed action may request “any other Federal agency which has jurisdiction by law,” or any such agency “which has special expertise with respect to any environmental issue” to be addressed in the EIS, to be a “cooperating agency.”68 The cooperating agency’s involvement and participation should be solicited at the earliest possible time.69 The regulations call for “scoping,” which is the “early and open process for determining the scope of issues to be addressed and for identifying the significant issues related to a proposed action.”70 As soon as it decides to prepare an EIS, the agency must publish a “notice of intent” in the Federal Register, subject to limited exceptions.71 The notice of intent invites “participation of affected Federal, State, and local agencies, any affected Indian tribe, the proponent of the action, and other interested persons.”72

After the scoping process, the EIS is issued in two stages. A draft environmental impact statement (DEIS) will issue “in accordance with the scope decided upon in the scoping process.”73 The DEIS should discuss “all major points of view on the environmental impacts of the alternatives including the proposed action.”74 At this juncture, the agency must invite comments.75 With respect to “any Federal agency that has jurisdiction by law or special expertise with respect to any environmental impact involved, or which is authorized to develop and enforce environmental standards,” the lead agency shall obtain comments.”76 It “shall request” comments of appropriate state and local agencies authorized to develop and enforce environmental standards; Indian tribes with a reservation that may suffer impacts; any agency which has requested statements on actions of the kind proposed; any applicant; and the public.77 The agency must “affirmatively solicit[] comments from those persons or organizations who may be interested or affected.”78

The agency then prepares the final environmental impact statement (FEIS). In doing so, the agency must “assess and consider comments both individually and collectively, and shall respond in one or more” of the following ways: (1) modify alternatives including the proposed action; (2) develop and evaluate alternatives not previously considered; (3) supplement, improve, or modify analyses; (4) make factual corrections; or (5) give a reasoned explanation for why the comments do not warrant further response.79

Several directives are clear from CEQ regulations regarding consultation with respect to an EIS. The agency is required to include federal, state, local, and tribal agencies, and the public, as well as to respond to commenters.80 The agency is not required to agree with the commenter, so long as the agency discloses an opposing point of view and reasonably responds to it. On the one hand, “disagreement among experts will not serve to invalidate an EIS.”81 On the other, a failure to disclose and respond to a commenter’s evidence and opinions directly challenging the scientific basis upon which the EIS rests will defeat it.82 The Ninth Circuit has explained that the NEPA requirement to address opposing viewpoints in an FEIS “reflects the paramount Congressional desire to internalize opposing viewpoints into the decision-making process to ensure that an agency is cognizant of all the environmental trade-offs that are implicit in a decision.”83 Once again, the NEPA burden is procedural: the agency must disclose and respond. The Administrative Procedure Act requires that the response must make sense; otherwise, the agency would reasonably be accused of acting in an arbitrary and capricious manner. Accordingly, a federal agency’s comments may be given extra weight over and above that of an ordinary citizen, depending on the agency’s expertise in the topic.

The obligations for public disclosure and comment with respect to an EA are entirely different. Unlike the rigid public/governmental comment requirements with respect to an EIS, agencies need only involve “environmental agencies, applicants, and the public” in preparing EAs “to the extent practicable.”84 Normally, the obligation of the agency in preparing a FONSI is to disseminate it to the affected public.85 In “certain limited circumstances,” however, the agency must make the FONSI “available for public review (including [through] State and areawide clearinghouses) for 30 days before the agency makes its final determination whether to prepare an [EIS] and before the action may begin.”86 There are two “limited circumstances”: where the proposed action “is, or is closely similar to, one which normally requires the preparation” of an EIS, or where its nature is “without precedent.”87

The federal courts have been inconsistent in their interpretations of the CEQ regulations with respect to public involvement in the EA process. On more than one occasion, the Ninth Circuit has held that a failure to involve the public constitutes a violation of the CEQ regulations. In Citizens for Better Forestry v. U.S. Department of Agriculture, the court stated: “Although we have not established a minimum level of public comment and participation required by the regulations governing the EA and FONSI process, we clearly have held that the regulations at issue must mean something. . . . It is evident, therefore, that a complete failure to involve or even inform the public about an agency’s preparation of an EA and a FONSI, as was the case here, violates these regulations.”88 And in Anderson v. Evans, the Ninth Circuit held that “[t]he public must be given an opportunity to comment on draft EAs and EISs.”89

By contrast, the First Circuit has held that CEQ’s public participation requirements are satisfied even when an agency has not offered a draft or final EA for public comment on grounds that “[n]othing in the CEQ regulations requires circulation of a draft EA for public comment, except under certain ‘limited circumstances.’”90 Similarly, the Tenth Circuit upheld an agency’s publication of an EA when the agency issued public notice of the proposed action and provided a comment period, even though the record did not clarify whether the EA was made available to the public before the agency issued its decision.91 And in Pogliani v. U.S. Army Corps of Engineers,92 the Second Circuit found that the plaintiffs were unlikely to succeed on their claim that the Corps erred by failing to release a draft EA and FONSI for public comment prior to its issuance in final form.

The District of Columbia federal district courts have inconsistently interpreted CEQ regulations. In Fund for Animals v. Norton,93 the U.S. District Court for the District of Columbia struck down as inadequate the publication by the U.S. Fish and Wildlife Service of the notice of the availability of a draft EA in the Federal Register, which afforded the public a two-week comment period followed two weeks later by finalization of the EA, and a week later by issuance of the FONSI. By contrast, the same court concluded that “an agency is not expressly required to circulate a draft EA for public comment before adopting its final decision, except in limited circumstances that do not apply here.”94 The court rejected the plaintiff’s argument that the agency was required to provide public opportunity to comment on a draft EA, noting that the CEQ regulation only required publication “to the extent practicable.”95 Accordingly, the court focused on the factual inquiry as to what had been “practicable” for the agency to accomplish in the EA process.

Timing—Supplemental Statements and Tiering

Generally, the appropriate time for preparing a NEPA document is prior to a decision, when the decision-maker has the widest range of options.96 When the decision results in an “irreversible and irretrievable commitment of resources,” NEPA review is required.97 One of the most difficult NEPA compliance questions presented to an agency is how to approach agency action that is ongoing, repetitive, or takes place in stages. Arguably, the largest federal programs with impacts on the physical world are always ongoing. The CEQ regulations address the process of considering impacts in consecutive NEPA document as “supplementing” NEPA review or “tiering” one NEPA document to another. In such cases, an earlier NEPA document is incorporated into a latter one.

Agencies must prepare “supplements to either draft or final [EISs]” if the agency “makes changes in the proposed action that are relevant to environmental concerns” or if “[t]here are significant new circumstances or information relevant to environmental concerns and bearing on the proposed action or its impacts.”98 The supplementing process is further described as follows:

[A]n agency need not supplement an EIS every time new information comes to light after the EIS is finalized. To require otherwise would render agency decision-making intractable, always awaiting updated information only to find the new information outdated by the time a decision is made. On the other hand, and as the petitioners concede, NEPA does require that agencies take a “hard look” at the environmental effects of their planned action, even after a proposal has received initial approval. . . . Application of the “rule of reason” thus turns on the value of the new information to the still pending decisionmaking process. In this respect the decision whether to prepare a supplemental EIS is similar to the decision whether to prepare an EIS in the first instance: If there remains “major Federal actio[n]” to occur, and if the new information is sufficient to show that the remaining action will “affec[t] the quality of the human environment” in a significant manner or to a significant extent not already considered, a supplemental EIS must be prepared.99

If information uncovered after a NEPA statement is sufficiently new and significant when compared to the information upon which the NEPA statement was based, a new NEPA statement is required.

The related concept of “tiering” addresses the sequencing of environmental statements generally from broad documents to narrower statements or analyses, or from a broad programmatic to a site-specific analysis. Tiering is defined in the CEQ regulations as “coverage of general matters in broader . . . with subsequent narrower statements or environmental analyses . . . incorporating by reference the general discussions and concentrating solely on the issues specific to the statement subsequently prepared.”100 The point of tiering is to allow an agency to avoid duplicating paper and effort. Assuming a broader NEPA document considers impacts, a narrower NEPA document can incorporate such consideration by reference. Impacts must be considered in some document, however, and if the agency does tier, the question is whether the analysis in the first NEPA document is sufficient to support tiering in the second one. In Kern v. Bureau of Land Management,101 the Ninth Circuit held that an environmental impact, consideration of which is eschewed in an EA, must necessarily have been addressed adequately in a NEPA document to which the EA is tiered.

As long as the necessary analysis of a particular action is undertaken at a relevant action point, supplementation and tiering are entirely accepted and common practices. In either case, a NEPA statement that is tiered to a final EIS, or which is supplemental to one, need not restate impacts analysis or alternatives that were already considered in the document it supplements or to which it is tiered. Nonetheless, a NEPA document may only be tiered under the CEQ regulations to a document that has itself been issued as a document under NEPA.102 Likewise, supplementation of NEPA documents can only occur in NEPA documents.

Because broad Federal programs are ongoing, tiering and supplementation can often become the rule rather than the exception. Questions surrounding such programs include when to begin a new programmatic review, when a new NEPA review may be required, and what requirements are imposed when supplemental or new information arises. In simplistic terms, if significant new information comes to light, a supplemental review document is required that could be tiered to a prior document. The staging of NEPA review cannot ultimately be employed to evade NEPA review of a particular impact or action. As sensible as these concepts may sound, the staging of NEPA review, and the avoidance of review that staging may unwittingly permit, are difficult questions for agencies to resolve.

Agency-Formulated Documents That Result From NEPA Compliance But Do Not Constitute NEPA Review

As the nation considers exploring for and producing energy from offshore frontiers, we have a new opportunity to do things right. It will take several years to fully implement the new safety regime this Commission has recommended—essential changes from doing business as usual in the Gulf of Mexico. But it is not necessary to put deepwater drilling on hold until all the changes are in place. The national and regional energy and economic imperatives can be reconciled effectively with the equally urgent needs to assure human safety and environmental integrity in the Gulf context, now and in the long term. Credit: Oil Spill Commission

NEPA compliance in the context of ongoing agency actions has given rise to certain practical problems for agencies attempting to determine whether they need to supplement NEPA analysis when NEPA documents already exist. If an agency undertakes actions that have already been subject to NEPA review and therefore do not require further NEPA analysis, the agency may nonetheless be challenged for moving forward without preparing any NEPA document. For this reason, agencies have established procedures outside the scope of the CEQ regulations to determine whether NEPA analysis already undertaken is sufficient such that no further review is required. Federal courts have upheld such agency procedures. In Pennaco Energy v. U.S. Department of the Interior,103 the Tenth Circuit addressed such a document—in this case, a [of NEPA Adequacy]—that had been prepared by DOI’s Bureau of Land Management (BLM) to determine what NEPA analysis existed, and whether more NEPA review should be undertaken to supplement it. While noting that “Of NEPA Adequacy, unlike EAs and FONSIs, are not mentioned in the NEPA or in the regulations implementing the NEPA,” the court upheld BLM’s use of “non-NEPA procedures to determine whether new NEPA documentation is required.”104 Though such documents cannot supplement previous EAs or []or address site-specific effects not previously considered in them, they identify for the decision-maker the location of existing NEPA analysis, and allow the decision-maker to determine whether more is needed.

Other agencies employ different terms for procedures to assess NEPA analysis.105 The critical point to note about these approaches is that, although they are legal means to assess the sufficiency of existing NEPA review; these procedures and documents are not NEPA documents and do not constitute NEPA review. Whether NEPA review is sufficient, preparation of a [of NEPA Adequacy]-type document depends on whether NEPA supplementation is required.

DOI’s Implementation of NEPA Procedures

Consistent with CEQ’s directives, DOI has promulgated regulations and guidance to ensure proper application of NEPA and CEQ’s binding rules. The regulations appear at 43 C.F.R. § 46, and generally reproduce and supplement CEQ’s directions. In addition, DOI has prepared a [Manual] that establishes guidance, direction, and requirements for, inter alia, the proper application of NEPA requirements to Departmental action. In addition to general Departmental guidance, the [Manual] gives specific direction to each bureau within the Department, including the former Minerals Management Service (MMS), which has been succeeded since the Macondo well (Macondo: The Gulf Oil Disaster) blowout last spring by the Bureau of Ocean Energy Management and Regulatory Enforcement (BOEMRE).106 The regulations and Manual provisions are detailed and lengthy. To avoid repeating the above analysis of NEPA, the following section mentions only provisions of note or interest to the Commission’s work.

DOI NEPA Rules

The regulations at 43 C.F.R. § 46 (“Implementation of [NEPA]”) generally repeat the requirements outlined in the CEQ rules. The Departmental rules make clear that use of pre-existing NEPA documentation, when further NEPA review would merely duplicate prior statements, should be a priority.107 The regulations address “incorporation of NEPA documents” and “tiered documents.”108 They also identify a document not mentioned in the CEQ regulations—a Finding of No New Significant Impacts (FONNSI). This document must follow the preparation of an EA and is distinguished from a FONSI in that it signifies the EA is tiered to a prior NEPA document (specifically an EIS), and the EA process has revealed that all significant environmental impacts were studied and any new impacts identified are not significant. The full text of this regulation is as follows:

An environmental assessment (Environmental Impact Assessment) prepared in support of an individual proposed action can be tiered to a programmatic or other broader-scope environmental impact statement. An environmental assessment may be prepared, and a finding of no significant impact reached, for a proposed action with significant effects, whether direct, indirect, or cumulative, if the environmental assessment is tiered to a broader environmental impact statement which fully analyzed those significant effects. Tiering to the programmatic or broader-scope environmental impact statement would allow the preparation of an environmental assessment and a finding of no significant impact for the individual proposed action, so long as any previously unanalyzed effects are not significant. A finding of no significant impact other than those already disclosed and analyzed in the environmental impact statement to which the environmental assessment is tiered may also be called a “finding of no new significant impact.”109

In its entirety, the regulation is accurate, but the italicized portion could be read as inconsistent with the CEQ regulations if taken out of context. It is not accurate to say that a FONSI can be reached for a proposed action with significant effects, even though it is true that a FONSI can be reached if all effects from the proposed action are addressed in a document to which the EA is tiered. By contrast, if incremental effects specifically caused only by the proposed action addressed in the EA are significant, and are not directly addressed in the EIS, a FONSI cannot be issued. The regulation’s creation of a new type of document (FONNSI) may confuse the proper application of NEPA in the case of tiering or supplementation for the public and for agency employees obligated to implement NEPA. Whether an effect of the action studied in the second NEPA document is fully addressed in the first NEPA document may be subject to debate.

The DOI’s rules also address “[c]onsultation, coordination, and cooperation with the agencies.”110 They appear to expand the consultation requirement established in the CEQ rules by directing consultation “whenever possible” for all NEPA documentation, not just EISs:

The Responsible Official must whenever possible consult, coordinate, and cooperate with relevant State, local, and tribal governments and other bureaus and Federal agencies concerning the environmental effects of any Federal action within the jurisdictions or related to the interests of these entities.111

The DOI NEPA rules provide specific requirements for consultation and notification in association with a Notice of Intent, the precursor to the EIS.112 Nonetheless, regulations specifically addressing EAs avoid any suggestion that these rules expand the CEQ consultation requirements for EAs. Instead, 43 C.F.R. § 46.305 repeats CEQ’s requirement that consultation is necessary only “to the extent practicable”; specifies that doing so is at the discretion of the Responsible Official113; ensures that the Department is not required to issue draft EAs and may do so only if the Official believes it to be “appropriate”; and permits the decision-maker to consult with Cooperating Agencies. The only mandatory requirements in the rules are to consider comments given, even if not solicited, and to “notify” the public of the final EA and FONSI. Comments on a FONSI generally do not need to be solicited, except as required by 40 C.F.R. § 1501.4(e)(2), a CEQ regulation that requires a 30-day notice for a FONSI to be published in “limited circumstances” defined by individual agencies.114

DOI’s rules detail the preparation of EAs and []in ways more extensive than the CEQ rules. Subpart D addresses EAs.115 Subpart E addresses EISs.116

The regulations also address CEs. Like the CEQ regulations, the Department defines a CE as “a category or kind of action that has no significant individual or cumulative effect on the quality of the human environment.”117 The rule goes on to note that “[e]xcept as provided in paragraph (c) of this section, if an action is covered by a Departmental CE, the bureau is not required to prepare” an EA or EIS.118 The reference to paragraph (c) is to the “extraordinary circumstances under which actions otherwise covered by a categorical exclusion require analyses under NEPA,” which are identified at 43 C.F.R. § 46.215. “Any action that is normally categorically excluded must be evaluated to determine whether it meets any of the extraordinary circumstances in section 46.215; if it does, further analysis and environmental documents must be prepared for the action.”119 Section 46.210 lists actions that constitute “Department-wide” CEs. Though the list is extensive, and includes personnel decisions and organizational changes, no items on the list pertain to management of oil and gas resources by any bureau.

The Departmental regulations establish the extraordinary circumstances that make an action otherwise a potential CE subject to NEPA review. “Extraordinary circumstances” exist for actions that:

  1. Have significant impacts on public health or safety.
  2. Have significant impacts on such natural resources and unique geographic characteristics as historic or cultural resources; park, recreation or refuge lands; . . . wetlands (EO 11990); floodplains (EO 11988); . . . migratory birds; and other ecologically significant or critical areas.
  3. Have highly controversial environmental effects . . .
  4. Have highly uncertain and potentially significant environmental effects or involve unique or unknown environmental risks.
  5. Establish a precedent for future action or represent a decision in principle about future actions with potentially significant environmental effects.
  6. Have a direct relationship to other actions with individually insignificant but cumulatively significant environmental effects.
  7. Have significant impacts on species listed, or proposed to be listed, on the List of Endangered or Threatened Species or have significant impacts on designated Critical Habitat for these species.120

Notably, the Department’s regulations add a category of exclusions from NEPA review not found in the CEQ rules—actions excluded by statute. “Congress may establish categorical exclusions by legislation, in which case the terms of the legislation determine how to apply those categorical exclusions.”121

[Manual]

For decades, DOI has issued “instructions, policies, and procedures that have general and continuing applicability to Departmental activities, or that are important to the management of the Department” in a [Manual].122 The [Manual] describes the organizations and functions of the Department’s bureaus and offices, delegations of the Secretary’s authority, and the policies and general procedures for administrative activities and the operations of specific programs. It is used to communicate the instructions of the Office of the Secretary throughout the Department, to provide guidance to the bureaus and offices in their administrative and program operations, and to serve as the primary source of information on organization structure, authority to function, and policy as well as general procedures. Bureaus and offices must comply with the provisions of the [Manual], except to the extent that the provisions are superseded by appropriate authority (e.g., a change in statute, regulation, an executive order; a secretary’s order, or a court decision).123

NEPA Procedures at Part 516 of the [Manual]

The lingering effects of the spill continue to significantly affect Louisiana's citizen’s way of life and the state's economy. The commercial and recreational fishing industries have been impacted and residents have not been able to enjoy the abundant seafood and outdoor opportunities as they have done for generations. Credit: State of Louisiana

The Department first proposed draft procedures to implement NEPA and the CEQ regulations on July 10, 1979.124 The first procedures were adopted as Part 516 of the [Manual] on March 18, 1980, to provide “policy and procedural directions to all elements of the Department for complying with the mandate of NEPA and the CEQ regulations.”125 The Department adopted a broad list of “Departmental Categorical Exclusions” in the [Manual], but explained that “[i]nstructions specific to bureaus will be issued [subsequently] as appendices to these procedures.”126 Adopting the language from the procedures proposed in 1979, the Department established criteria “to determine actions to be categorically excluded from the NEPA process.”127 The criteria are as follows:

  1. The action or group of actions would have no significant effect on the quality of the human environment.
  2. The action or group of actions would not involve unresolved conflicts concerning alternative uses of available resources.128

The [Manual] goes on to note:

Based on the above criteria, the classes of actions listed in Appendix 1 to this Chapter are categorically excluded Department-wide from the NEPA process, Bureaus shall list categorical exclusions specific to their programs in the Bureau Appendix to Chapter 6.129

In Chapter 6, the [Manual] directs “heads of Bureaus and offices to “propose categorical exclusions.”130 As described below, these provisions remained in place until 2009, when Chapters 1-6 of the [Manual] were amended and all references to CEs and exceptions to their use were removed.

[Manual] Offshore CEs

From the first Departmental oil and gas NEPA compliance review, the United States Geological Survey (USGS) defined certain key approvals in the Western and Central Gulf of Mexico as categorically excluded from NEPA review, including: applications for permits to drill (APD); exploration plans (EP); and development and production plans (DPP); and then, as amended later, development operations and coordination documents defined by MMS.131

The USGS’s decision to treat Gulf of Mexico (Minerals Management Service (MMS)) planning documents and the drilling of wells in this region as exempt from NEPA review appears to have stemmed from statutory provisions in, and congressional commentary associated with, passage of the Outer Continental Shelf Lands Act (OCSLA) amendments of 1978. Although USGS has never explained its decision to treat EPs as categorically excluded, USGS may have believed that DPPs were statutory CEs, which could not be subject to regulatory exception. USGS also treated APDs in the Western Gulf region the same as it treated other applications for the Outer Continental Shelf—categorically excluded as effectively “tiered” to approved planning documents. This conclusion was a questionable application of the CE, as defined by CEQ, for the entire Outer Continental Shelf, but improper in the Western Gulf because no tiering to a CE (a non-NEPA document) is allowed. MMS later came to believe that planning documents in the Western Gulf were categorically excluded from NEPA review because they met the CEQ definition of a CE, even though MMS regulations acknowledged that such planning document approvals did have significant impacts on the human environment in other Outer Continental Shelf regions. MMS squared neither its understanding of how the USGS CEs came into being nor its contradictory description of the effects on the human environment of approvals of the same planning documents, as occurring or not occurring depending on a geographic boundary.

By the time the relevant approvals were given for the Macondo well (Macondo: The Gulf Oil Disaster), all of these problems undercut the use of CEs. Even if the categorical exceptions, as applied to APDs and planning documents in the Western Gulf, could be squared today, it is questionable whether MMS properly applied these exceptions to the circumstances presented by deepwater wells (United States experience in the deepwater Gulf of Mexico).

The convoluted history of defined CEs for offshore oil and gas development stems from a statute, is developed through the [Manual], and coincides with regulations enacted by relevant bureaus. The basis for the Department’s determination that the APDs, EPs, DPPs, and DOCDs in the Western Gulf are categorically excluded from NEPA review seems to have been poorly understood by the MMS. In particular, Notices to Lessees changed the application of the rules in critical ways.132 Provisions of regulations cited in the [Manual] have been superseded, compounding problems with interpreting what does and does not apply offshore. The following discussion attempts to extract the story of the creation and maintenance of the CEs by examining the text and legislative history of the OSCLA 1978 amendments, the pertinent parts of the [Manual], and the Departmental regulations. The discussion reveals seeming inconsistencies with the discussion of NEPA in Part 1 of this paper. Accordingly, the following points must be kept in mind:

  1. Other than citing to the 1978 amendments to OCSLA and regulations implementing that statute, how the Department derived CEs for DPPs (or DOCDs) in the Western Gulf region was not articulated when they were created.
  2. Staff research has not determined why the USGS concluded that approval of EPs for the Western Gulf of Mexico (Minerals Management Service (MMS)) region should constitute a CE.
  3. To the extent the Department defined Western Gulf EPs and DPPs as CEs based on its reading of the OCSLA amendments of 1978, this was not a result of a statutory mandate by Congress.
  4. If MMS believed that relevant CEs were in place because of a statutory mandate, it would be inappropriate for it to undertake to review whether exception to the CE should occur because of extraordinary circumstances, because the exception could not override a statutory provision.
  5. Approval of the planning documents defined to be CEs has not been specifically identified by any Departmental bureau not causing impacts on the environment, and therefore fitting within the CEQ definition of a CE.
  6. If the Department believed the relevant CEs were in place because they met the CE definition in the CEQ rules or Departmental regulations, then any approval (APD, EP, DPP, DOCD) would have to be reviewed to ensure that a particular action is not an unusual circumstance calling for NEPA review before being categorized as a CE.
  7. APDs are categorically excluded from NEPA review if the subject wells are identified in an approved plan (EP, DPP, DOCD) that, outside the Western Gulf region, would be subject to NEPA review. In the Western Gulf region, the plans to which an APD is “tiered” are not subject to NEPA review because they are identified as CEs. Such “tiering” to non-NEPA documents is improper.

The Source of the Western Gulf of Mexico Offshore Categorical Exclusions—OCSLA Amendments of 1978

The OCS is a significant source of oil and gas for the Nation’s energy supply. The approximately 43 million leased OCS acres generally accounts for about 15 percent of America’s domestic natural gas production and about 27 percent of America’s domestic oil production. BOEMREs oversight and regulatory framework ensure production and drilling are done in an environmentally responsible manner, and done safely. Credit: BOEMRE

In 1978, Congress enacted Public Law 95-372 to amend OCSLA. A single provision, section 25, is the source of the CEs in the [Manual]. Section 25 (codified at 43 U.S.C. § 1351), which addresses “oil and gas development and production,” is particularly relevant for two mains reasons. First, it adds a requirement that OCS lessees must submit a detailed DPP for approval by DOI, which, at least once in an area or region, shall be considered a “major Federal action significantly affecting the quality of the human environment” and thus require an EIS.133 Section 25 establishes extensive consultation requirements for these plans and terms for coordination with coastal zone management provisions. Second, section 25 explicitly excepts the Gulf of Mexico region from its terms. In an exception to that exception, Congress added a final subsection (l) that permits the Secretary of the Interior to apply section 25 to leases in the Eastern Gulf of Mexico.134 The end result is that the OCSLA, as written today, requires Outer Continental Shelf lessees to submit DPPs, and requires that at least once for each area such a plan must be subject to an EIS, except in the Western Gulf of Mexico, where these requirements do not apply.

The legislative history surrounding the OCLSA 1978 amendments shows that competing factors produced these amendments. High energy prices in the late 1970s combined with America’s increasing dependency on foreign oil prompted a call for increased development in undeveloped Outer Continental Shelf areas, and for a quick turnaround on actual production once the leases were issued. As the legislative history explained:

Until December 1975, the OCS leasing program was confined almost exclusively to the Gulf of Mexico. The only exception was a small area leased off southern California in the Santa Barbara Channel. […] If we are to increase our OCS oil and gas development, leasing must take place in new or “frontier” areas.135

The history of the amendments further describes “steps already taken in that direction,” including President Carter’s directive that CEQ study environmental impacts of oil and gas production on the Atlantic and Gulf of Alaska Outer Continental Shelf, an acceleration in leasing from 1 million acres in 1973 to 10 million acres in 1975, and a DOI Federal Register request for comment on 17 potential Outer Continental Shelf oil and gas leasing areas.136 Concern also stemmed from the 1969 Santa Barbara oil spill. Congress wanted to ensure increased oversight of development and production, through the plans identified in section 25, with concomitant environmental protection, state and local consultation provisions, and coordination with Coastal Zone Management Act requirements. This was “one of the most important provisions.”137 Each lessee was required to submit a DPP with “information about the nature and extent of the proposed development, including . . . environmental safeguards and safety standards to be implemented.”138 The DPP was subject to consultation with the governors, local officials, and the public.139

The industry expressed concerns about additional environmental review, stating that it was a “constraint[] to expanded production.”140 The Government Accounting Office reported that industry representatives demanded “timely, efficient, and effective methods for environmental assessment and realistic assessment of tradeoff[s] between energy needs and environmental hazards.”141 Indeed, the American Petroleum Institute suggested that the additional NEPA and consultation requirements could add three to six years to the time between leasing and production.142

Section 25 manifested something of a compromise. In the OCSLA 1978 amendments, DPPs subject to NEPA and consultation requirements were compulsory in frontier areas, but not in the Gulf of Mexico or the Santa Barbara Channel, where development was well-established.143 The legislative history includes correspondence illustrating a debate about these issues among Congress, Federal agencies, the Secretary of the Interior, and the industry. In a letter to the Senate Subcommittee on Energy and Natural Resources Chief Counsel dated May 10, 1977, the Secretary of the Interior explained the reasoning behind the exception for lessees in the Gulf and Santa Barbara Channel, but expressed concerns about this exception. He proposed alternative language that would permit DOI to make case-by-case determinations as to whether a DPP might be advisable even in the excepted regions:

One of the most significant changes in S. 9 and H.R. 1614 of existing practice is the detailed review and state participation required prior to approval of development and productions plans. Approval of these plans will in many cases require preparation of an [EIS]. An EIS would be required, for example, at least once prior to major development in any area or region of the OCS. These are addressed in section 25 of the bills. Section 25, however, excludes the Santa Barbara Channel and the Gulf of Mexico from its requirements. We believe the Secretary should have the option, where necessary, of applying the provisions of section 25 in these two areas. The Santa Barbara Channel and the Gulf of Mexico have been well developed within recent years and the purpose for the general exclusion in section 25 is understandable. There may be, however, more areas of the Channel or the Gulf where application of these provisions is advisable. Therefore, we recommend addition of the following language as section 25(k) . . . .

“An oil and gas lease issued or maintained under this Act which is located in the Gulf of Mexico or the Santa Barbara Channel shall be subject to the provisions of this section if the Secretary determines, pursuant to regulations prescribed by [him], that the likely environmental or onshore impacts of the development and production of such lease make the application of the provisions of this section in the public interest.”144

The Secretary of the Interior’s suggested provision was not adopted. In the final version of the OCSLA amendments of 1978, the Santa Barbara exception was removed, and the final subsection (l), ensuring that Department could apply section 25 in the Eastern Gulf of Mexico, was added. The Western Gulf, however, remained an exception to any requirement of a DPP, which in section 25 was “at least once” the subject of an EIS. As the August 10, 1978, Conference Report explained:

The House amendment requires a development and production plan to be submitted for all future leases in a frontier area. The Senate bill provides for a development and production plan to be submitted for all future leases anywhere. The conference report requires a plan to be submitted for all future leases except in the Gulf of Mexico.

The House amendment also requires a plan to be submitted for existing leases in frontier areas, where no oil or gas has been yet discovered. The Senate bill similarly requires a plan to be submitted for existing leases where there has not yet been a discovery, but exempts the Gulf of Mexico. The conference report adopts the Senate language. Thus, the mandate and specific procedures of this bill that the Secretary of Interior must secure submission, and then review, approve, or disapprove a development and production plan applies to new leases or existing leases where there has not yet been a discovery and does not apply to leases, old or new, in the Gulf of Mexico.

The requirements of this new section are specifically made inapplicable to the Gulf of Mexico. However, there are areas in the eastern gulf that have never been developed. . . . The conferees therefore adopted a provision that gives the Secretary of the Interior the discretion to require submission of plan[s]–in accordance with this section–for development and production activities in this area which is defined as being adjacent to the State of Florida.145

The statute, as amended by section 25 of the OCSLA amendments of 1978, remains in effect. Subsection (b) prohibits development of a lease anywhere on the OCS “other than the Gulf of Mexico” without a DPP.146 Subsection (e)(1) requires a DPP everywhere else to be subject to an “at least once” EIS: “At least once the Secretary shall declare the approval of a development and production plan in any area or region (as defined by the Secretary) of the outer Continental Shelf, other than the Gulf of Mexico, to be a major Federal action.”147 Likewise, the exception from the exception appears in subsection (l): “The Secretary may require the provisions of this section to apply to an oil and gas lease issued or maintained under this subchapter, which is located in that area of the Gulf of Mexico which is adjacent to the State of Florida.”148

Whatever the legislative history may reflect about Congress’s intentions with respect to additional NEPA review in the Western Gulf, the statutory language controls the proper interpretation of the OCSLA 1978 amendments. The statutory language was precise about what must happen outside the Western Gulf OCS region—mandatory DPPs for all leases and an EIS at least once rules the Department can now or could then have imposed in the Western Gulf were less obvious. But the statute did not prohibit NEPA review of Federal action there; it made the requirements of section 25 inapplicable there.

The statute also addresses EPs. The provisions codified at 43 U.S.C. § 1340(c) require lessees to submit EPs and require the Secretary to approve such plans within 30 days of submission. The statute does not address whether the plans qualify as major Federal actions significantly affecting the human environment, nor does it except or address the Gulf of Mexico.149 In addition, the statute permits the Secretary to require lessees to submit an APD for a permit to drill in accordance with an approved EP.150

[Manual] Offshore Categorical Exclusions

NOAA responds to an explosion and fire on a deepwater semisubmersible drilling platform some 50 miles SE of the Mississippi Delta. The incident on the DEEPWATER HORIZON occurred at approximately 11:00 PM on 20 April with more than 120 crew reported aboard. Credit: BOAA

At the time of the first publication of the [Manual], responsibility for addressing Outer Continental Shelf activity fell to the USGS. The USGS proposed its NEPA compliance procedures, and also its first [Manual] CEs, in 1980.151 From these first proposals, USGS identified all APDs as categorically excluded so long as they were described in an approved EP or DPP.

In the Western Gulf of Mexico, however, USGS also excluded the EP or DPP from the NEPA process.152 The only explanation for this was a citation to USGS offshore rules implementing the OCSLA amendments of1978. Without articulating its logic, USGS thus suggested that the statute itself prohibited NEPA review of both DPPs and EPs in the Western Gulf of Mexico. At a minimum, USGS may have believed that construing section 25’s exception for DPPs in that region in any other manner would provoke a controversy. USGS gave no reason for concluding that Western Gulf EPs would be categorically excluded. It proposed the following CEs:

  • (24) Approval of an Application for Permit to Drill (APD) an OCS oil and gas exploration or development well when said well is described in an approved exploration plan, development plan, or production plan. . . . .
  • (36) Approval of OCS exploration plans in the Western Gulf of Mexico (30 C.F.R. § 250.2). . . .
  • (37) Approval of OCS development/production plans in the Western Gulf of Mexico (30 C.F.R. § 250.2).153

Proposed CEs 27-30 addressed onshore APDs as CEs. Acknowledging that DPPs likely addressed action that would cause (according to Congress, at least) significant impacts, USGS noted that elsewhere such plans would likely require an EIS. USGS listed as “major actions normally requiring an EIS”:

Approval of an OCS oil and gas development and production plan in a frontier area, when the plan is declared to be a major Federal action in accordance with Section 25 of the OCS Lands Act Amendments of 1978 (30 C.F.R. § 250.34-4).154

The proposed USGS [Manual] provisions were approved as a final appendix to the Department’s NEPA procedures on January 19, 1981, and published in the Federal Register on January 23, 1981.155 Without further examining differences between the Western Gulf and other areas of the Outer Continental Shelf, USGS cited the OCSLA amendments of 1978 and 30 C.F.R. § 250. It did, however, reinforce the distinctions in response to comments. One commenter requested a change requiring []for all DPPs except in the Gulf of Mexico. USGS disagreed and stated that it would “follow the environmental review process established in 30 C.F.R. § 250.34.”156 USGS explained: “We will, in any area or region of the OCS, except in the Western Gulf of Mexico, prepare at least one development/production plan EIS pursuant to subsection 25(e) of the OCS Land[s] Act Amendments of 1978.”157

The final appendix revised the order of CEs and separated onshore oil and gas CEs from offshore ones.158 But in concept the offshore CEs were unchanged. The final CEs appeared in Part 2.4 of the USGS appendix to Chapter 6 of the [Manual]. The offshore CEs were as follows:

  • (b) Approval of an OCS exploration or development/production plan in the Western Gulf of Mexico (30 C.F.R. § 250.2) which does not require an environmental report from an operator pursuant to item 3 of To Lessee 80-6. . . .
  • (d) Approval of an APD for an oil and gas exploration or development well when said well and appropriate mitigation measures are described in an approved exploration plan, development plan, or production plan.159

The [Manual] was amended in 1986, after the establishment of and transfer of oil and gas responsibilities to MMS. MMS addressed oil and gas development in Appendix 10 to Chapter 6, which was approved August 12, 1986. The [Manual] was reorganized again on May 27, 2004. Appendices produced by individual bureaus within the Department were assigned chapter numbers, and MMS’s CEs were placed in Chapter 15. The critical elements of the original USGS CEs, however, never changed: An APD for any offshore well is categorically excluded from NEPA review so long as it is described in an approved plan for exploration, development, production, or operations; and, in the Western Gulf, such plans are themselves categorically excluded from the NEPA process. Other changes were significant, however. MMS separated the Western from the Central Gulf regions but defined plans submitted for offshore leases within both to be CEs. MMS added the newly created DOCD—the counterpart to the DPP required to be submitted by Gulf lessees—as a CE. And MMS revised the CEs for planning documents to ensure that exceptions were available in particular environmental situations. As currently written, the offshore CEs are as follows:

  • (10) Approval of an offshore lease or unit exploration[,] development/production plan or a Development Operation Coordination Document in the central or western Gulf of Mexico (30 C.F.R. § 250.2) except those proposing facilities: (1) In areas of high seismic risk or seismicity, relatively untested deep water, or remote areas; or (2) within the boundary of a proposed or established marine sanctuary, and/or within or near the boundary of a proposed or established wildlife refuge or areas of high biological sensitivity; or (3) in areas of hazardous natural bottom conditions; or (4) utilizing new or unusual technology. . . .
  • (12) Approval of an Application for Permit to Drill (APD) an offshore oil and gas exploration or development well, when said well and appropriate mitigation measures are described in an approved exploration plan, development plan, production plan, or Development Operations Coordination Document.160

The language italicized above is important. The addition of exceptions to the CEs for particular circumstances where environmental damage could be severe only makes sense if MMS necessarily recognizes that the basis for the CE is not a statutory mandate but rather the CEQ definition of a CE—an action not normally causing an effect on the quality of the human environment. If the reason for the CE is a mandatory statutory exclusion from NEPA, the statute cannot be overridden by a regulatory exception.161 Previously, USGS had never suggested that approval of an EP or DPP met the definition of a CE. To the contrary, Congress defined approval of a DPP as something normally causing significant impacts that required an EIS at least once. This significant change in the language raises questions about the basis for the CEs.

It remains true that approval of plans outside portions of the Gulf of Mexico “normally” require an EIS. The OCSLA 1978 amendments continue to be the source of that [Manual] provision.162 Nonetheless, the fact that MMS came to believe the CEs were founded in the CEQ and Departmental definitions was also reinforced elsewhere in the 2004 [Manual], which specifies, consistent with the CEQ regulations and with 43 C.F.R. § 46, that a CE cannot apply to a proposed action if one of the exceptions to the application of CEs pertains. The MMS CEs, reorganized in 2004, state that “the following MMS actions are designated categorical exclusions unless the action qualifies as an exception under Appendix 2 of 516 Manual 2.”163

This statement is decidedly problematic. First, the statement would not be true, if (as USGS originally suggested) the CE was mandated by law.164 Second, Chapters 1-6 of the [Manual] was revised in 2009 and condensed into four chapters. Nothing in the 2009 version of Chapters 1-4 defines a CE or specifies the exceptions to the application of CEs that were present in Chapter 2 in 2004 when MMS’s Chapter 15 was created.

It is important to note that the remainder of the [Manual], as amended, does properly refer back, as it must, to the superior application of the CEQ regulations and Departmental regulations at 43 C.F.R. § 46. Chapter 1 states that it “supplements the CEQ and DOI regulations and must be read in conjunction with both.”165 Elsewhere Chapter 1 specifies that in case of any discrepancies among Departmental guidance, “Departmental regulations at 43 CFR 46 and 516 [Manual] 1-4 shall govern.”166 MMS’s Chapter 15, however, became more and more attenuated from its original purpose, MMS regulations, and the [Manual] itself. If, in fact, Department regulations govern in the case of a discrepancy between MMS regulations and the [Manual], and the statute is not the source of the CEs for EPs, DPPs, and DOCDs, then it is questionable whether the CEs are valid in the absence of some reasonable determination showing that approval of such plans is “a category or kind of action that has no significant individual or cumulative effect on the quality of the human environment.”167

Departmental Rules Implementing OCSLA Amendments of 1978

Under the Oil Pollution Act of 1990, "responsible parties" are strictly liable for cleanup costs and certain damages resulting from the spill. While liability for cleanup costs is unlimited, liability for damages (such as impacts on fisheries) is capped at $75 million for offshore facilities. There is little assurance that a "responsible party" causing a future spill will have sufficient resources to fully cover the cost of damages. Credit: Oil Spill Commission

USGS promulgated rules applicable to offshore oil and gas operations that exempted lessees in the Western Gulf region from the requirement to prepare a DPP. In regulations incorporated into the CEs adopted by USGS and later MMS, codified at 30 C.F.R. § 250, the Department defined the Western Gulf of Mexico and addressed “compliance with [[[NEPA]]].”168 In this latter regulation, which otherwise addressed NEPA review in association with EPs and DPPs, the Department made clear that USGS must “declare the approval of a development and production plan” in “the OCS, except in the western Gulf of Mexico, to be a major federal action at least once pursuant to subsection 25(e) of the Act.”169 This regulation was promulgated on September 14, 1979.170 USGS’s final 1981 CEs cross-referenced these rules.

Later, on several occasions, MMS redesignated and amended these regulations to incorporate extensive and specific requirements for the submission of EPs and DPPs.171 These changes amended Part 250, which addresses whether the OCSLA amendments of 1978 prohibit the Department from requiring DPPs in the Western Gulf; accordingly. MMS created a “development operations coordination document,” or DOCD, which was a substitute document required only in the Western Gulf region:

Development and Production Plans are not required for leases in the western GOM. For these leases, the lessee shall submit to the Regional Supervisor for approval a Development Operations Coordination Document with all information necessary to assure conformance with the Act, other laws, applicable regulations, lease provisions, or as otherwise needed to carry out the functions and responsibilities of the Regional Supervisor.172

References to DPPs include these Gulf of Mexico DOCDs.173 These regulations specified, as in the OCSLA 1978 amendments, that the Department would evaluate the environmental impacts of a DPP at least once in an EIS, except in the Western Gulf of Mexico.174

In 2005, MMS again revised Part 250. Though MMS outlined several of its changes, it explained that the purpose of the amendments was to codify directives to lessees already in place in Notices to Lessees.175 This rulemaking contained particular requirements for the contents of EPs, DPPS, and also DOCDs: consultation, environmental review, addressing of direct and cumulative effects on onshore and offshore environments resulting from implementation of EPs, DPPs, and DOCDs.176

In the preamble to this rulemaking, MMS addressed its NEPA processes, including the CEs, in a way indicating that MMS was unaware USGS had established the CEs by citing the OCSLA 1978 amendments; of the fact that DPPs must, at some point, be subject to an EIS; or of the fact that a CE is excepted from the NEPA review process rather than a part of it. MMS correctly explained that it “must comply with” NEPA, and relevant regulations.177 But it went on to state, “According to NEPA requirements, MMS must prepare an [(EA)] in connection with its review of plans for activities on the OCS . . . . The appropriate MMS Region prepares these analyses for every plan received.” However, the NEPA regulations (40 C.F.R. § 1508.4) do allow agencies to exclude categories of actions from the preparation of an EA or an EIS when agency procedures have demonstrated that these actions—individually or cumulatively—do not have a significant impact on the environment.

MMS follows the procedures outlined in the [Manual]178 to categorically exclude routine OCS lease or unit plans in the Western and Central Gulf of Mexico areas unless certain exceptions are present. Some exceptions pertain to the nature of the proposed activity, and others to the nature of potential environmental impacts that may result from the activity. When MMS processes plans using a Categorical Exclusion Review, the agency reviews the proposed activity and the potential environmental impacts at the proposed site. These actions do not require MMS to prepare an EA, and MMS may limit the information that the lessee/operator is required to submit unless the information is required for compliance with other Federal laws. MMS prepares an EA in its review of plans that meet the criteria of the specified exceptions to the CE criteria or will prepare an EIS. Whether MMS reviews plans through the Categorical Exclusion Review or EA process, the agency requires that environmental impacts be avoided or diminished to an acceptable level through plan amendments or conditions MMS imposes during the plan approval process.179

Thus, by 2005, MMS was asserting that DOCDs submitted for portions of the Gulf are categorically excluded from NEPA review because they are “routine” and, by definition, not the sort of action that will have an impact on the quality of the human environment. At the same time, MMS believed that elsewhere planning documents normally require EAs (instead of the “at-least-once” EIS). In addition, MMS regulations at 43 C.F.R. § 250 addressed environmental requirements with respect to DOCDs, and treated them as the same as DPPs. For all planning documents, the regulations compelled submission of documents for purposes of NEPA review, reflecting the view that environmental impacts could result from the approvals. These positions about the nature of effects resulting from approval of planning documents cannot be squared.180

NEPA Issues Surrounding the Macondo Well

Question 1—Categorical Exclusions

In the near term, the Alaskan frontier is likely to attract the greatest attention, and to require the closest scrutiny. The interest in Alaska reflects the likelihood of finding significant new sources of oil in the Chukchi and Beaufort Sea areas off Alaska’s north coast. The Alaskan Arctic is characterized by extreme cold, extended seasons of darkness, hurricane-strength storms, and pervasive fog—all affecting access and working conditions. And oil-spill response efforts are complicated year-round by the remote location and the presence of ice, at all phases of exploration and possible production. Credit: Oil Spill Commission

MMS concluded that actions in approving the Exploration Plan and APD for the Macondo well (Macondo: The Gulf Oil Disaster) fell within CEs, and therefore were not subject to NEPA. By CEQ’s definition, these actions were therefore in a “category of actions which do not have a significant effect on the human environment and which have been found to have no such effect in procedures adopted by a Federal agency in implementation of the regulations (§ 1507.3) and for which, therefore, neither an [[[EA]]] nor an [EIS] is required. . . . .”181 Because the idea that drilling a deepwater well on the Outer Continental Shelf is the sort of action that “does not have a significant effect on the human environment” appears, with hindsight, to be inherently illogical, the question arises whether BLM properly applied the CE procedures.

DOI’s precise stance on these topics is unclear. Soon after enactment of the OCSLA 1978 amendments and the 1978 CEQ regulations, USGS created CEs in the Western Gulf. It categorically excluded from NEPA review all exploration, development, and production plans, and applications for permits to drill (so long as they were addressed in an approved plan). In doing so, USGS never identified such plans as actions, as defined by the CEQ or DOI, that are within the category of actions not having a significant impact on the human environment. Instead, by citing the OCSLA 1978 amendments, USGS implied that the law compelled CEs. That this happened in 1980-81 (as the [Manual] provisions moved from draft to final) is not surprising given the legislative history of the OCSLA 1978 amendments. Section 25 of the OCSLA1978 amendments, however, addressed DPPs but excepted the Western Gulf region from its application. This is not the same thing as saying that Federal action in that region would be exempt by law from NEPA review.

By regulation, MMS later created a new planning document for approval in the Gulf—a DOCD—thus seemingly acknowledging that section 25 of the OCSLA 1978 amendments did not define the Gulf as excluded from the regulation requiring planning documents. If that is the case, by analogy it seems unlikely that NEPA exemption for the region is compelled by section 25.

As the years passed, MMS appeared to lose sight of how the CEs came into being. Without questioning whether they were properly defined as CEs, MMS presumed that they were properly defined, and applied exceptions to the CEs in locations where particular types of environmental effects might be felt. Thus, MMS came to act as if the CEQ and Departmental definitions of an action, which do not normally have an effect on the human environment, properly applied to approvals of EPs, DPPs, and DOCDs in the relevant Gulf regions, while enforcing regulations that made clear that the same approvals in other regions could not meet that definition and required EAs and EISs.182 It seems difficult to sustain such competing views of the environmental impacts of the same planning documents based solely on lines drawn on a map. MMS has never precisely addressed the justification for its employment of CEs. By employing terms such as “Categorical Exclusions Review” for the process to decide whether an agency action should fall within a CE found in the [Manual], the inference could be drawn (and may have been intended by MMS) that the Categorical Exclusion Review was a third level of NEPA review rather than a plain exemption from NEPA review—the quintessential definition of a CE in CEQ’s regulations.183

With respect to the Macondo well (Macondo: The Gulf Oil Disaster), MMS conducted NEPA review at the lease planning stage and the lease sale stage. Relevant to the use of CEs, however, MMS considered an EP for Lease 206 (the lease on which the Macondo well was drilled), an amended EP, and four APDs. In every case, MMS applied CEs.184 There are several problems with these decisions by MMS.

First, it is not clear why, 29 years into the consistent agency declaration of CEs, these leases were defined as CEs in the first place. The rationale behind the CE for the exploration plans was not explained. While it has been suggested that USGS categorically excluded EPs in the Gulf because of the 30-day approval requirement of the OCSLA,185 this time frame applies throughout the Outer Continent Shelf under that statute. Yet, EPs in other regions are subject to NEPA under 43 C.F.R. § 250, as discussed by MMS in the preamble to its 2005 rules. The finding that the Gulf region EPs are exempt from NEPA review seems to be inexplicable.

Second, to the extent that the agency came to believe the OCSLA 1978 amendments did not compel the CEs, there seems to be no basis for the implicit conclusion that approvals of EPS, DPPs, or DOCDs in the Gulf region are actions that do not have an impact on the human environment. The same planning documents were found to require NEPA review in agency rules at 30 C.F.R. § 250, and, therefore, without a sensible explanation for the difference, the continued employment of CEs in the Gulf region on this basis is suspect.

Third, the APDs are subject to CEs when the well to which they pertain is subject to an approved planning document. While it does not constitute NEPA review, a CE is a product of NEPA and CEQ regulations. The fact that an action is the subject of another NEPA document, and therefore does not require duplicate NEPA review, is an effect of tiering. Defining APDs as categorically excluded from NEPA (except in the context of Energy Policy Act CEs, which are identified by law) is a questionable extension of the tiering concept. Further, to the extent that defining approval of APDs as categorically excluded derives from the notion that it is unnecessary to do another NEPA review because one was already done for the planning document, this logic does not and cannot apply when the planning document was not subject to NEPA in the first place. No NEPA review can be tiered to a non-NEPA document, and a CE is not a NEPA document. Accordingly, application of the CEs for APDs to any geographical place, though long-standing, has inherent logical flaws; application in the Western Gulf of Mexico where the planning documents were never subject to NEPA review at all would seem unsustainable.

Fourth, even assuming that the planning documents were properly defined as categorically excluded from NEPA review, and the CEQ and Departmental regulations were the source for their designation as CEs, it follows that MMS was obligated by regulation to question whether any of the exceptions applied based on extraordinary circumstances.186 Without reproducing the list of exceptions, it does not seem clear that MMS seriously undertook the task of examining this list carefully. The notion that the largest oil spill in American history resulted from a blowout on a well that had been defined by the agency as exempt from NEPA because it is an action “which do[es] not have a significant effect on the human environment”187 indicates that the application of the CEQ definition was off-kilter and the exceptions were not sufficiently examined. The concern goes beyond after-the-fact logic. The exceptions to the application of a CE include actions which “[h]ave highly uncertain and potentially significant environmental effects or involve unique or unknown environmental risks.”188 The May 2000 Gulf of Mexico Deepwater Operations and Activities EA expressly discussed the potential for a deepwater spill and the length of time needed to control one (60-120 days); it concluded that “further investigation is needed” to evaluation the consequences of a deepwater blowout.189 Given the actual events after the blowout took place, it is clear that such investigation was never completed. How a deepwater EP escaped NEPA review under the exception to CEs is difficult to understand.

Question 2—Consultation

For years, federal efforts to regulate offshore oil and gas drilling have suffered due to cross-cutting purposes, pressure from political and industry interests, a deepening deficit of technical expertise, and inadequate resources for agencies that oversee offshore drilling, particularly the Minerals Management Service (MMS). Credit: Oil Spill Commission

Since the blowout (Macondo: The Gulf Oil Disaster), much has been made of the fact that MMS did not fully appreciate or address comments of sister or local agencies in the NEPA process. Although MMS was not obligated to agree with other agencies’ comments, MMS was obligated to respond in the []to which the Macondo well approvals ultimately were tiered, and to “assess and consider comments . . . and respond” in one of the manners required in 40 C.F.R. § 1503.4. The question of whether MMS properly considered agency and public comments with respect to the lease sale EA should be answered on a case-by-case basis to determine whether MMS considered comments to the extent practicable.190 In both cases, to the extent MMS addressed comments, its response was required to be well-reasoned, and could not be arbitrary.

The basis for much of the concern regarding the adequacy of consultation and coordination stems, as with the concern for the adequacy of NEPA review at all, from the employment of CEs for the EPs and APDs for the Macondo well (Macondo: The Gulf Oil Disaster). MMS’s general regulations regarding planning documents are nonspecific as to the kind of NEPA review anticipated and do not clarify how consultation will occur, instead leaving that question of compliance with the CEQ and Departmental NEPA rules. In addition, the regulations call for documents in association with DPPs and DOCDs that are not, by rule, provided to the public, and so, even with NEPA compliance, it is unclear what the public or local agencies may see in the context of NEPA review. It does seem, however, that, to the extent the agency considered the action to be categorically excluded from NEPA review, no NEPA compliance would take place at all that would effectuate consultation. Accordingly, the question of MMS’s compliance with consultation requirements in the context of CEs is strictly derivative. If the use of the CE was appropriate, then consultation in association with NEPA review is not at issue because there was no NEPA review.

MMS regulations governing the planning documents presume the applicability of all relevant laws, including NEPA, and do not address the CEs for planning documents in the Gulf. They do not precisely duplicate NEPA regulations, either those prepared by CEQ or DOI. For example, with respect to environmental compliance, the regulations require the lessee to submit an environment impact analysis (EIA),191 for purposes of allowing MMS to “comply[] with the National Environmental Policy Act (NEPA) of 1969 and other relevant Federal laws.”192 With respect to consultation, the regulations address the lessee’s obligation to inform MMS of the lessee’s consulting history: “Your EIA must include a list of agencies and persons with whom you consulted, or with whom you will be consulting, regarding potential impacts associated with your proposed exploration activities.”193 The requirements for DPPs and DOCDs are the same. The lessee must submit an EIA for these planning documents,194 for purposes of allowing MMS to comply with, inter alia, NEPA.195 And, as with EPs, the regulations specify that the lessee must describe its own consultation activities with respect to DPPs or DOCDs.196 In addition, deepwater operators must submit a “deepwater operations plan” that “provides sufficient information for MMS to review a deepwater development project, and any other project that uses non-conventional production or completion technology.”197 The deepwater operations plan must be accompanied by a “Conceptual Plan” for the project.198 The regulations at 30 C.F.R. § 250.286 through 250.295 detail the requirements for these documents, but contain no requirements pertaining to notification of the public, consultation with local agencies, or compliance with NEPA. The deepwater operations plan and Conceptual Plan do not substitute for but do supplement the DPP or DOCD. Similarly, the lessee submitting a DPP or DOCD must also submit a conservation information document.199 Once again, these regulations do not describe NEPA or consultation.

From these regulations, one must surmise that MMS, when preparing appropriate NEPA reviews for EPs and DPPs or DOCDs, will conduct appropriate consultation. Much information, however, is submitted in association with DPPs and DOCDs—with the deepwater operations plans and conservation information documents—that is not, by rule, publicized to interested parties, and thus would only be publicly available if provided in association with a properly-prepared NEPA review document. If the DPP or DOCD is only considered as an EA, such information would be provided “to the extent practicable.” By contrast, material that is a part of the DPP or DOCD is subject to specific review and consultation provisions of the MMS operations rules.

This discussion of rules relating to planning documents, and associated NEPA review, is only of tangential interest in the Western Gulf, where the agency employs CEs for their approval. The MMS operations regulations are silent about CEs, or how their use affects MMS’s decisions with respect to consultation. In the preamble to the 2005 rulemaking, MMS explained that it might choose to limit the material the lessee would otherwise be required to submit if MMS decided that a plan approval is categorically excluded. In the case of a CE, “MMS may limit the information that the lessee/operator is required to submit unless the information is required for compliance with other Federal laws.”200 Accordingly, in the case of a CE, it is not entirely clear that MMS would even demand compliance with requirements of the operations rules related only to NEPA.

In conclusion, because consultation with respect to an EA or EIS is governed by NEPA rules promulgated by CEQ and the DOI, and is only necessary “to the extent practicable” for EAs, it is not at all clear what information is normally available to the public or to appropriate local agencies, how it is disseminated, or whether there is an opportunity to consult or comment in association with an EA prepared for a planning document. But in the Western Gulf of Mexico, where planning documents are categorically excluded by [Manual], as indicated in Notices to Lessees, no NEPA consultation would take place at all, and MMS may, by [to Lessee]s, limit the information required to be submitted by the lessee.

Question 3—Reasonably Foreseeable Impacts

Drilling in deepwater does not have to be abandoned. It can be done safely. Offshore oil and gas will continue to be an important part of the nation’s domestic energy supply for many decades. The future of domestic oil production will rely to a substantial extent on outer continental shelf sources and further development of deposits there, in progressively deeper, more distant waters.

The NEPA documents that sought to examine the risk of an oil spill considered the possibility of a blowout the size of the 2010 event to be so unforeseeable that these documents did not address it. Although MMS did not examine a type of blowout of the nature that occurred as a “worst case scenario” in the relevant NEPA documents, BP apparently did look at a worst case discharge for the purpose of its Oil Spill Response Plan, which is an appendix to the EP.201 In this document, BP addressed a potential spill of up to 300,000 barrels per day. Possibly because the EP to which the Oil Spill Response Plan was appended was identified as a CE, this projection was never included in any NEPA study by MMS. As a purely NEPA question, then, this paper asks whether sufficient information was available to justify a more detailed analysis by MMS of a large-scale oil spill in relevant NEPA analyses on grounds that such an impact was reasonably foreseeable.

Several factors undercut MMS’s decision to address potential spills in its NEPA documents (Programmatic EIS, Multi-Sale EIS, and Lease Sale 206 EA), all the while eschewing any discussion of a blowout of a significant nature before the blowout took place. To the extent such a discussion would be found to be legally required, the location of the discussion would have been in an EIS to which subsequent documents are tiered. Conversely, a FONSI for an EA, such as the Lease Sale 206 EA, may have been unwarranted if a spill of the size projected in the Oil Spill Response Plan had been addressed in an EA. If a blowout of this magnitude was reasonably foreseeable for purposes of the Oil Spill Response Plan, it is hard to imagine how such a spill would not be a reasonably foreseeable impact to be examined under NEPA.202 MMS appears to have relied on geographic boundaries (in this case a geopolitical boundary) for classifying the foreseeability of impacts of the Ixtoc spill off the coast of Mexico in 1979. Whether a repeat event was reasonably foreseeable would depend on an explanation why what happened in 1979 could not happen again, or why it was too “speculative” or unduly remote.203

This question is now academic. Whatever was true about what was reasonably foreseeable to consider by way of effects before the Macondo blowout (Oil spill), it would be arbitrary hereafter for MMS to undertake NEPA review without considering the sort of effects that resulted from the Macondo well blowout as reasonably foreseeable. The question of what is reasonably foreseeable has two components. What must the agency consider? And does it compel an EIS?204 While it can be debated whether the likelihood of another blowout of the magnitude of the Deepwater Horizon spill (Oil spill) is so small that an EIS is unnecessary, this might be a hard sell absent the inclusion of specific mitigation measures capable of reducing the risk below that necessary to trigger an EIS. Absent such mitigation, MMS will likely be required at some stage of its decision-making process to prepare an EIS of some nature that considers such effects, to which other NEPA documents may be tiered.

End Notes

1 Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 558 (1978). but seeks

2 Kleppe v. Sierra Club, 427 U.S. 390, 410 n.21 (1976).

3 Baltimore Gas & Electric Co. v. Natural Resources Defense Council, Inc., 462 U.S. 87, 97 (1983).

4 Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350-51 (1989).

5 42 U.S.C. § 4321.

6 See Robertson, 490 U.S. at 349.

7 Id. at 350-51 (citations, footnote omitted); Marsh v. Oregon Natural Resources Council, 490 U.S. 360, 371 (1989).

8 42 U.S.C. § 4332(2).

9 42 U.S.C. § 4332(2)(C).

10 42 U.S.C. § 4332(2)(C)(i)-(v).

11 42 U.S.C. § 4332(2)(E).

12 See, e.g., Sabine River Authority v. U.S. Department of the Interior, 951 F.2d 669, 675 (5th Cir. 1992), citing Metropolitan Edison Co. v. People Against Nuclear Energy, 460 U.S. 766 (1983) (NEPA is triggered by “physical change in the environment”).

13 40 C.F.R. § 1500 et seq.

14 40 C.F.R. § 1500.3.

15 40 C.F.R. § 1500.2(b); 1507.3(a).

16 40 C.F.R. § 1501.3; 1501.4.

17 40 C.F.R. § 1508.11.

18 40 C.F.R. § 1508.9.

19 See 40 C.F.R. § 1507.3(b).

20 40 C.F.R. § 1508.13.

21 Id.

22 Id.

23 See 40 C.F.R. § 1508.20.

24 40 C.F.R. § 1508.9(a)(3).

25 40 C.F.R. § 1508.10.

26 40 C.F.R. § 1508.22.

27 40 C.F.R. § 1501.4(a)(2).

28 40 C.F.R. § 1502.

29 Id. C.F.R. § 1502.19 and 1502.25.

30 40 C.F.R. § 1508.9(b).

31 42 U.S.C. § 4332(2)(C) (EIS required when significant impacts are found).

32 40 C.F.R. § 1502.16 (EIS includes discussion of “adverse environmental effects which cannot be avoided”).

33 490 U.S. at 352-53 (footnote and citation omitted).

34 5 U.S.C. §§ 704-06.

35 Marsh, 490 U.S. 360; see also 40 C.F.R. § 1502.24 (agencies must “insure the professional integrity, including scientific integrity” of analyses in EISs).

36 42 U.S.C. § 4332(2)(C), (E); 40 C.F.R. § 1502.1; Kleppe, 427 U.S. at 410 n.21; Natural Resources Defense Council, Inc. v. Hodel, 819 F.2d 927, 929 (9th Cir. 1987).

37 State of California v. Block, 690 F.2d 753, 761 (9th Cir. 1982), quoting Trout Unlimited v. Morton, 509 F.2d 1276, 1283 (9th Cir. 1974); Scientists’ Institute for Public Information v. Atomic Energy Commission, 481 F.2d 1079, 1092 (D.C. Cir. 1973).

38 5 U.S.C. § 706.

39 Cabinet Mountains Wilderness v. Peterson, 685 F.2d 678, 681-82 (D.C. Cir. 1982); Maryland-National Capitol Park & Planning Commission v. U.S. Postal Service, 487 F.2d 1029, 1040 (D.C. Cir. 1973).

40 40 C.F.R. § 1508.10.

41 40 C.F.R. § 1500.4 (“Reducing paperwork”).

42 40 C.F.R. § 1500.4(p) (citing40 C.F.R. § 1508.4).

43 40 C.F.R. §1507.3.

44 40 C.F.R. § 1508.4.

45 951 F.2d at 679.

46 40 C.F.R. § 1500.4(p).

47 40 C.F.R. § 1507.3(b)(2)(ii).

48 40 C.F.R. § 1502.16; 1502.14.

49 40 C.F.R. § 1508.7.

50 40 C.F.R. § 1502.16(h).

51 40 C.F.R. § 1508.9(b).

52 40 C.F.R. § 1508.8; 1508.25(c).

53 40 C.F.R. § 1508.8(a).

54 40 C.F.R. § 1508.8(b).

55 Metropolitan Edison, 460 U.S. at 774-75.

56 40 C.F.R. § 1508.7.

57 Id.

58 40 C.F.R. § 1502.22.

59 Id.

60 51 Fed. Reg. 15624.

61 Id.

62 490 U.S. at 356.

63 40 C.F.R. § 1502.22(b)(1).

64 Id.

65 40 C.F.R. § 1500.2(d).

66 40 C.F.R. § 1501.6.

67 40 C.F.R. § 1506.6(a).

68 40 C.F.R. § 1501.6.

69 40 C.F.R. § 1501.6(b).

70 40 C.F.R. § 1501.7.

71 Id. (see 1507.3(e) (notice may be issued closer to the time the EIS is prepared)).

72 40 C.F.R. § 1501.7(a).

73 40 C.F.R. § 1502.9(a).

74 Id.

75 40 C.F.R. § 1503.1.

76 40 C.F.R. § 1503.1(a)(1).

77 40 C.F.R. § 1503.1(a)(2)-(4).

78 40 C.F.R. § 1503.1(a)(4).

79 40 C.F.R. § 1503.4(a).

80 E.g., Center for Biological Diversity v. U.S. Forest Service, 349 F.3d 1157, 1168-69 (9th Cir. 2003).

81 Life of the Land v. Brinegar, 485 F.2d 460, 472 (9th Cir. 1973).

82 Center for Biological Diversity, 349 F.3d at 1169.

83 California v. Block, 690 F.2d 753, 771 (9th Cir. 1982).

84 40 C.F.R. § 1501.4(b).

85 40 C.F.R. § 1501.4(e)(1).

86 40 C.F.R. § 1501.4(e)(2).

87 Id.

88 341 F.3d 961, 970 (9th Cir. 2003).

89 314 F.3d 1006, 1016 (9th Cir. 2002).

90 Alliance to Protect Nantucket Sound, Inc. v. U.S. Department of Army, 398 F.3d 105, 115 (1st Cir. 2005).

91 Greater Yellowstone Coalition v. Flowers, 359 F.3d 1257, 1279 (10th Cir. 2004).

92 306 F.3d 1235, 1238-39 (2d Cir. 2002)

93 281 F. Supp. 2d 209, 226-27 (D.D.C. 2003)

94 Biodiversity Conservation Alliance v. U.S. Bureau of Land Management, 404 F. Supp. 2d 212, 220 (D.D.C. 2005).

95 404 F. Supp. at 220, citing 40 C.F.R. § 1501.4(b).

96 Environmental Defense Fund v. Andrus, 596 F.2d 848, 852-53 (9th Cir. 1979).

97 Mobil Oil Corp. v. FTC, 562 F.2d 170, 173 (2nd Cir. 1977); Sierra Club v. Peterson, 717 F.2d 1409, 1414-15 (D.C. Cir. 1983).

98 40 C.F.R. § 1502.9(c)(1).

99 Cf. 42 U.S.C. § 4332(2)(C).; Marsh v. Oregon Natural Resources Council, 490 U.S. at 373-74 (footnotes omitted).

100 40 C.F.R. § 1508.28.

101 284 F.3d 1062, 1074 (9th Cir. 2002).

102 Kern, 284 F.2d at 1074.

103 377 F.3d 1147, 1162 (10th Cir. 2004).

104 Id.

105 The U.S. Forest Service uses a “validation and verification” procedure.

106 On June 18, 2010, Secretary of the Interior Ken Salazar ordered that the Minerals Management Service be officially renamed the Bureau of Ocean Energy Management, Regulation, and Enforcement (BOEMRE). For consistency, throughout this paper, we will refer to the agency as the Minerals Management Service. As of the writing of this paper, the [Manual] has not been changed to acknowledge the BOEMRE.

107 43 C.F.R. § 46.120(d) (“Responsible Officials should make the best use of existing NEPA documents by supplementing, tiering to, incorporating by reference, or adopting previous NEPA environmental analyses to avoid redundancy and unnecessary paperwork.”)

108 43 C.F.R. § 46.135; 46.140.

109 40 C.F.R. § 46.140(c) (first italics added; second in original).

110 43 C.F.R. § 46.155.

111 Id.

112 43 C.F.R. § 46.435.

113 Id.

114 43 C.F.R. § 46.305(c).

115 43 C.F.R. § 46.310; 46.315; 46.320; 46.325.

116 43 C.F.R. § 46.400; 46.405; 46.415; 46,420; 46.425.

117 43 C.F.R. § 46.205.

118 43 C.F.R. § 46.205(a).

119 43 C.F.R. § 46.205(c)(1).

120 43 C.F.R. § 46.215.

121 43 C.F.R. §. 46.205(d).

122 11 [Manual] 1.1.

123 11 [Manual] 1.2.

124 44 Fed. Reg. 40436.

125 45 Fed. Reg. 27541.

126 45 Fed. Reg. 27542.

127 516 [Manual] 2.3.A(1) (1980). 44 Fed. Reg. 40439 (July 10, 1979) (copied in final at 45 Fed. Reg. 27544 (Apr. 23, 1980)).

128 516 [Manual] 2.3.A(1) (1980).

129 Id. at 2.3A(2).

130 Id. at 6.4.A(3).

131 Ultimately, MMS created three Gulf of Mexico areas: Western, Central, and Eastern. For purposes of NEPA, MMS grouped the Western and Central areas together.

132 This paper does not separately document the extensive Notices to Lessees that have applied to CEs.

133 See Public Law 95-372, section 25 at subsections(a)(1), (b), and (e).

134 Id. at section 25(l).

135 Report No. 95-284, the Subcommittee on Energy and Natural Resources Report to Accompany S. 9 (June 21, 1977) at 50.

136 Id.

137 Id. at 82.

138 Id. at 83.

139 Id. at 82.

140 Id. at 62.

141 Id.

142 Id. at 144-45.

143 Id. at 83.

144 Id. at 154-55.

145 Id. at 115-16.

146 43 U.S.C. § 1351(b).

147 43 U.S.C. § 1351(e)(1).

148 43 U.S.C. § 1351(l).

149 Id.

150 43 U.S.C. § 1340(d).

151 45 Fed. Reg. 75336 (Nov. 14, 1980).

152 See 516 [Manual] 2.4.A(2) (1980).

153 45 Fed. Reg. 75336-37 (CEs listed in the Chapter 6, draft USGS appendix Part 2.4).

154 Draft USGS appendix Part 2.3, 45 Fed. Reg. 75336 (Nov. 14, 1980).

155 46 Fed. Reg. 7485.

156 Id.

157 Id. (emphasis added).

158 Part 2.4.B(2)(a)-(h), at 46 Fed. Reg. 7487 (Jan. 23, 1981) (onshore CEs). Congress subsequently created a “rebuttable presumption” that certain onshore APDs are categorically excluded from NEPA review in section 390 of the Energy Policy Act of 2005, Pub. L. No. 109-58, 119 Stat. 594. 42 U.S.C. § 15942(a) and (b). The presumption exists generally if the wells are foreseeable in a NEPA document prepared in the previous five years.

159 Appendix 5 at 2.4.B(3) (1981), published at 46 Fed. Reg. 7487 (Jan. 23, 1981).

160 516 [Manual] 15.4.C (2004 and 2010).

161 See 43 C.F.R. § 46.205(d).

162 516 [Manual] 15.4 (2004 and 2010) (“Major Actions Normally Requiring an EIS”).

163 Emphasis added.

164 43 C.F.R. § 46.205(d).

165 516 [Manual] 1.1 (2010) (Purpose).

166 516 [Manual] 1.8.C (2010) (Mandate).

167 43 C.F.R. § 46.205.

168 30 C.F.R. § 250.34-4.

169 30 C.F.R. § 250.34-4(d).

170 44 Fed. Reg. 53700.

171 See 63 Fed. Reg. 29479, 29485 (May 29, 1998).

172 30 C.F.R. § 250.204(d)(1) (2000).

173 43 C.F.R. § 250.200.

174 43 C.F.R. § 250.204(j).

175 70 Fed. Reg. 51478 (Aug. 30, 2005).

176 E.g., 30 C.F.R. § 250.227 (EPs).

177 70 Fed. Reg. 51478 (Aug. 30, 2005).

178 516 [Manual] 15 (2010).

179 Id. (emphasis added).

180 The Congressional Research Service’s June 4, 2010 Report on the Deepwater Horizon Oil Spill quotes MMS as stating that CEs are available when “the impacts from the common operations are expected to be negligible to non-existent based upon general information gathered during past environmental analysis.” Congressional Research Service, The 2010 Oil Spill: The Minerals Management Service (MMS) and the National Environmental Policy Act (NEPA) at 12 (June 4, 2010). The source of the cited MMS document at CRS’s Appendix C is unclear. To the extent the quote is from an MMS paper or statement, it reflects some confusion about the proper definition of a CE. If, in fact, MMS found during regular NEPA document review that a particular type of agency action routinely had “negligible/non-existent” impacts, it would have been necessary for MMS to officially define such action as a CE based on the CEQ definition as a direct result of such experience with NEPA review, or else continue to perform NEPA review, which presumably would result in FONSIs. But no such event occurred. The CEs for DPPs and EPs were put in place for the Western Gulf region almost 30 years ago, when the first NEPA [Manual] was established.

181 40 C.F.R. § 1508.4.

182 30 C.F.R. § 250. See also MMS , Oil and Gas Leasing, Exploration & Development Process, Figure 1 (depicting EAs and []for EPs and DPPs).

183 40 C.F.R. § 1500.4(p).

184 See Council on Environmental Quality, Report Regarding the Minerals Management Service’s National Environmental Policy Act Policies, Practices, and Procedures as They Relate to Outer Continental Shelf Oil and Gas Exploration and Development CEQ, Figure 2 (Aug. 16, 2010) CEQ Report.

185 43 U.S.C. § 1340.

186 43 C.F.R. § 46.205; 46.210; 46.215.

187 40 C.F.R. § 1508.4

188 43 C.F.R. § 46.215(d). Though MMS employed CEs for the EP, MMS’s operational regulations defined deepwater development as “non-conventional.” 30 C.F.R. § 250.286.

189 CEQ Report at Chapter II, pages 16-17.

190 40 C.F.R. § 1501.4(b).

191 30 C.F.R. § 250.227.

192 30 C.F.R. § 250.227(a)(3).

193 30 C.F.R. § 250.261(d).

194 30 C.F.R. § 250.261.

195 30 C.F.R. § 250.261(a)(3).

196 30 C.F.R. § 250.261(d).

197 30 C.F.R. § 250.286(a).

198 30 C.F.R. § 250.286(b).

199 30 C.F.R. § 250.296-250.299.

200 70 Fed. Reg. 51478 (Aug. 30, 2005).

201 See 30 C.F.R. § 250.213. This rule requires a lessee to append the following to its EP: “Blowout scenario. A scenario for the potential blowout of the proposed well in your EP that you expect will have the highest volume of liquid hydrocarbons. Include the estimated flow rate, total volume, and maximum duration of the potential blowout. Also, discuss the potential for the well to bridge over, the likelihood for surface intervention to stop the blowout, the availability of a rig to drill a relief well, and rig package constraints. Estimate the time it would take to drill a relief well.”

202 40 C.F.R. § 1508.8(b).

203 40 C.F.R. § 1502.22; Metropolitan Edison, 460 U.S. at 774-75.

204 Inland Empire Public Lands Council v. Schultz, 992 F.2d 977, 981 (9th Cir. 1988) (“Both connected actions and unrelated but reasonably foreseeable future actions may result in cumulative impacts that can trigger an EIS.”); Save the Yaak Comm. v. Block, 840 F.2d 714, 721 (9th Cir. 1988).

Citation

(2011). The National Environmental Policy Act and Outer Continental Shelf oil and gas activities. Retrieved from http://editors.eol.org/eoearth/wiki/The_National_Environmental_Policy_Act_and_Outer_Continental_Shelf_Oil_and_Gas_Activities